So on Friday the remainder of the first floor slab was completed. This only took half a day because again they had the use of a JCB- a bit of a luxury here in Malawi! We also had our first storm on Saturday, signifying the onset of the Rainy season (worst in Nov- March). The columns on the first floor should go up quickly, and then the brickwork, leaving only the roof as the remaining external structure. The cladding on the ground floor is also underway giving us a glimpse of the appearance of the final building.